20.79.01.08

.08 Completeness Determination and Availability of CPCN Applications and Related Materials for Proposed New and Modified Power Plants

A. A person shall submit a CPCN application to construct a new or modified generating station to the Commission, which shall, within 45 days of issuing an order either delegating the CPCN application to the Utility Law Judge Division, or keeping it at the Commission, acknowledge receipt of the request and indicate whether the request is either:

(1) Complete and the Commission will proceed to review the request; or

(2) Deficient, in which case the Commission shall specify the nature of the deficiency.

B. A copy of the CPCN application to construct a new or modified generating station, as well as any public comments and State agency comments and recommendations thereon, shall be available for public inspection at the offices of the Commission.