20.50.09.05

.05 Interconnection Request Processing Fees.

A. A utility may only charge a small generator interconnection application fee for a Level 2, Level 3, or Level 4 interconnection.

B. The small generator facility interconnection fee under §A of this regulation may not exceed the following:

(1) No charge for Level 1 applications;

(2) $50 plus $1 per kW of rated generating facility output for Level 2 applications; and

(3) $100 plus $2 per kW of rated generating facility output for Level 3 and 4 applications.

C. The utility shall specify the interconnection processing fees charged under this regulation in its tariff.