09.12.81.04

.04 Final Acceptance Inspection.

A. A final acceptance inspection by the Commissioner is required before the Commissioner may issue a certificate of registration and inspection on all new or modified elevator units.

B. A contractor shall request a final acceptance inspection at least 30 days before the date the contractor requests for the final acceptance inspection to be conducted.

C. A contractor may cancel a scheduled inspection under this regulation by written notice to the Commissioner at least 24 hours before the scheduled inspection.